Sutton’s quietest train station is set for a major transformation which will double the number of trains stopping there.
Belmont station was only this week revealed as the least-used of the borough’s nine stations, with an estimated 215,108 entries and exits during 2025/26. But the overlooked station could soon become much busier, with plans to increase its service from just two trains an hour to four.
Belmont’s platform will be extended by 45 metres towards Sutton, bringing it to 205 metres and allowing 10-car trains to use the station.
Passengers will also notice major changes around the station itself. A new customer information screen, CCTV and lighting will be installed, while part of the existing platform will be improved and the track realigned to reduce stepping distances between trains and the platform.
Behind the scenes, the railway will undergo an extensive signalling overhaul needed to accommodate the increased service. Three new signals will be installed and two existing ones moved, alongside new warning and train protection equipment, signalling cabinets and telephones.
The overhaul comes as the enormous London Cancer Hub continues to grow nearby, bringing thousands of jobs and potentially far more passengers to the area. Anchored by the Institute of Cancer Research and The Royal Marsden NHS Foundation Trust, the hub is being developed into a major centre for cancer research, life sciences and innovation.
It is expected to eventually support 13,000 jobs and contribute £1.2 billion a year to the UK economy, making improved public transport connections increasingly important. The Belmont Capacity Enhancement Project aims to make sure the railway can cope with that growth while giving residents a more frequent service.
A welfare compound began being installed on August 27, with piling works due to run from October 6 until December 2. Passengers will then face a series of weekend engineering works as the transformation takes shape.
These include installing the new pre-cast concrete platform in December, carrying out platform and signalling works during several weekends in early 2027 and resurfacing the platform in April. The new signalling system is scheduled to be commissioned and enter service during works from August 29 to 31, 2027.
The project is being funded by Sutton Council with support from the Government’s Levelling Up Fund, with the wider aim of improving transport capacity and supporting the area’s future growth.
The investment is particularly striking given just how quiet Belmont currently is. Its 215,108 estimated entries and exits last year placed it 1,409th nationally and made it Sutton’s least-used station. Sutton station, by comparison, recorded almost 4.87 million entries and exits, more than 22 times as many.
But with twice as many trains, longer platforms and the London Cancer Hub growing on its doorstep, Sutton’s quietest station could be about to get a whole lot busier.